Analysis of possible external forces and their distribution,.
Formulation of assumptions for the model.
Literature review and best practice analysis for the load cases.
However, if you investigate, for example, the load cases simulation and analysis step, you will find that it can be split further into a set of the smaller tasks: These sub-tasks should be shown in the Gantt Chart, such that the customer can monitor the accomplishment of the design project.
Preparation of the manufacturing drawings.
Vehicle load cases simulation and analysis of the results.
Development of the vehicle model for the load cases simulation.
Conceptual and embodiment design of the body.
However, any phase or any step of the project development always consists of the multiple smaller tasks, which may not be practical to report to the customer.Īn engineering team must design a composite body for an electric truck. Gantt Chart is an efficient tool for the customer to control progress of a project and the work on its different phases. Beside this, various Gantt Chart templates can be found in different applications, e.g., in MS Excell.An example of a Gantt Chart in the capstone design project is shown in Table 1.Ī Gantt Chart can be built for an entire project, or just for its individual phase, for example, for the manufacturing process, as you can see in Table 2. project planning, project management, or project scheduling software) is offered on the market. To facilitate the use of Gantt charts for the engineers and managers, special Gantt chart software (a.k.a.
Correlations between the tasks, their grouping, links and overlapping.
What tasks should be accomplished in the project.
It is very important to define which tasks need to be completed before others can start. To build a chart, all tasks involved in the project must be clearly stated, personnel’s responsibilities for each task should be defined, duration of the tasks must be specified, possible problems should be evaluated. The chart allows project managers to break down a project into manageable work phases, stay organized, and visualize dependencies between tasks. They outline tasks constituting a project, their sequence and milestones, shown against a timescale. If a deadline is missed or a sequence of tasks is violated, it may negatively affect the entire project, delay it or lead to unforeseen complications.Īn important tool to control workflow and visually convey information on the project progress are the Gantt charts. For a successful and timely completion of a project you must monitor a large number of various activities, their progress, schedule and deadlines.